1.Walk me through how MRP decides what to order and when.
Why they ask
They want to know you understand the logic behind the screen, not just which button runs it.
How to answer
- Start from gross requirements coming off the master schedule and exploding through the bill of materials
- Net against on-hand inventory, open purchase orders and safety stock
- Offset by lead time to get planned order release dates
- Mention lot sizing rules and how bad master data, like a wrong lead time, throws the whole thing off