1.Walk me through planned value, earned value and actual cost, and what the indices tell you.
Why they ask
It's the floor. If you stumble here, nothing else in the interview matters.
How to answer
- Define each in plain terms: budget for work scheduled, budget for work performed, cost of work performed
- Explain CPI as earned over actual and SPI as earned over planned, and what above or below parity means
- Point out that SPI drifts back toward parity near the end of a program even when it's late, so you'd also check the critical path
- Give a quick example from a control account you've worked